Output type: transistor output, drain type.
Output points: 8 points.
OFF leakage current: 0.1mA.
Output protection function.
Rated load voltage / current: DC24V/DC24V/0.1A.
External connection: 2 wire.
Fast connector type.
Simple wiring through quick connector.
Can be installed along the 6 direction.
In order to facilitate the form of simulation to generate the actual state of the scene,
Create the necessary environmental conditions for the operation of the program.
The simulation debugging has two forms of hardware simulation and software simulation.
Input type: DC input, negative public end.
Input points: 16 points.
Enter the response time: 1.5ms the following.
Rated input voltage / current: DC24V/5mA.
External connection: 4 wire.
Fast connector type.
Simple wiring through quick connector.
Can be installed along the 6 direction.
MITSUBISHI PLC program simulation debugging
The basic idea of program simulation debugging is,
In order to facilitate the form of simulation to generate the actual state of the scene,
Create the necessary environmental conditions for the operation of the program MITSUBISHI AJ65VBTCU2-8T
AJ65VBTCU2-8T
Depending on the way the field signals are generated,
The simulation debugging has two forms of hardware simulation and software simulation. Pulse input: differential input MITSUBISHI AJ65VBTCU2-8T.
Preset input: differential input.
Count range: 0~16777215.
Number of stations: 4 stops.
Station type: remote equipment station.
Configuration of master / local station,
In addition to the other site network with different CC-Link in addition to the main station and the remote station configuration can also be the main station and the local station configuration.
A local PLC can communicate with the master station PLC and other remote workstations MITSUBISHI AJ65VBTCU2-8T.
MITSUBISHI PLC hardware implementation
Hardware implementation is mainly for the control cabinet and other hardware design and field construction.
Design control cabinet and the operating table and other parts of the electrical wiring diagram and wiring diagram.
Electrical interconnection diagram of each part of the design system.
According to the construction drawings of the site wiring, and carry out a detailed inspection.
Because the program design and hardware implementation can be carried out at the same time,
So the design cycle of the MITSUBISHI PLC control system can be greatly reduced.
MITSUBISHI PLC online debugging.
On-line debugging is the process that will through the simulation debugging to further carry on thee on-line unification to adjust AJ65VBTCU2-8T.
On-line debugging process should be step by step,
From MITSUBISHI PLC only connected to the input device, and then connect the output device, and then connect to the actual load and so on and so on stepp by step AJ65VBTCU2-8T.
If you do not meet the requirements, the hardware and procedures for adjustment.
Usually only need to modify the part of the program can be.