LK Automation Limited LK Automation Limited
Download Sort: MITSUBISHI
Home >> Manual Download
MITSUBISHI A970GOT-TBA-EU Introductory Manual Manual A970GOT-TBA-EU Operating Manual
Product model: A970GOT-TBA-EU
Name: touch screen
Brand: MITSUBISHI
Sort: Introductory Manual Operating Manual
File language: English
Input type: DC input, positive public end / negative public end.
Input points: 16 points.
Enter the response time: 1.5ms the following.
Rated input voltage / current: DC24V/7mA.
External connection: 3 wire.
According to the external connection mode and the external equipment input and output specifications,
Choose from a rich product lineup A970GOT-TBA-EU Introductory Manual Manual A970GOT-TBA-EU Operating Manual A970GOT-TBA-EU
Finger protection through the upper part of the terminal,
The human body will not be exposed to live parts,
Therefore, the terminal station type remote I/O module can be directly mounted to the machine tool. RS-232 2 channel.
Transmission speed: 2 channel total is 115.2kbps.
Equipment layer / field bus CC-Link device layer is the PLC and other control devices and sensors and drive devices connected to the field network,
Network for the lowest layer of the whole network system A970GOT-TBA-EU Introductory Manual Manual A970GOT-TBA-EU Operating Manual.
Using CC-Link field bus connection, the number of wiring is greatly reduced,
Improve the maintainability of the system.
And, not just the amount of data ON/OFF and other switches,
Can also be connected to the ID system, bar code reader, inverter, man-machine interface and other intelligent devices,
From the completion of a variety of data communication, the management of the terminal production information can be realized,
On the centralized management of the state of the machine movement,
Make maintenance work efficiency also greatly improved A970GOT-TBA-EU Introductory Manual Manual A970GOT-TBA-EU Operating Manual.
Q series PLC in the use of CC-Link function better,
And easier to use. DC input points: 16 points.
Input voltage and current: 3/7mA, DC12/24V.
Response time: 10ms.
Positive pole sharing.
16 point /1 a public side.
Output points: 12 points.
Output voltage and current: DC12/24V, 0.5A/1 point, 3.2A/1 common end.
Response time: 2ms.
8 point /1 a public end, 4 point /1 a public end.
Output form: transistor output, leakage type.
36 point terminal station.
Number of stations: 4 stops.
Compact remote I/O unit.
According to the control requirements of the system, using the appropriate design method to design MITSUBISHI PLC program.
Procedures to meet the requirements of system control as the main line,
Write one by one to achieve the control function or the sub task of the program,
Gradually improve the functions specified by the system.
MITSUBISHI PLC detection, fault diagnosis and display and other procedures.
These procedures are relatively independent, generally in the basic completion of the program design and then add.
Hardware simulation method is to use a number of hardware equipment to simulate the generation of the signal,
The signals are connected to the input end of the PLC system in a hard wired way, and the timeliness is strong.
Software simulation method iss in the MITSUBISHI PLC in the preparation of a set of simulation program,
The simulation provides the field signal, which is simple and easy to operate, but it is not easy too guarantee the timeliness A970GOT-TBA-EU Introductory Manual Manual A970GOT-TBA-EU Operating Manual A970GOT-TBA-EU Introductory Manual Manual A970GOT-TBA-EU Operating Manual.
Simulation of the process of debugging, debugging method can be used to segment, and the monitoring function of programmer.